Certified Scrum Master

I had been thinking about taking the 2-day Certified Scrum Master (CSM) training for couple of years. Last week I finally got to the course with a colleague. My concern was that since I mainly develop firmware, I would not benefit that much from the course. I could not have been more wrong. I highly recommend CSM course to anyone involved with project work. Even if you do not believe in agile development, this course can still give you pointers on where to improve your work.

We got our training from Boris Oestergard and Jens Gloger. They have been giving in-house training in finland earlier, at least at Nokia Networks, Sulake and Accenture. We had also Bas Vadde from Nokia Networks giving an interesting guest speak about scaling Scrum to larger programs of hundreds of developers.

You can see our group photo at www.scrum.dk (photos).

9/20/2006

Just Nail That One Thing

I have become to value that the team should be imposed to only one new thing at the time. For example bringing in team room, pair development or TDD should not happen in a huge bang but a transformation time is needed. However when I had a chance to run an agile day with senior management I forgot this important lesson. I got over ambitios and tried to achieve too many things at the time.

1. I started with presentation covering agile development philosophy, results from our experiment and also the needs for more advanced future adaptation. All this in 1.5 hours with active discussion. Try to keep your presentations focused.

2. We then applied Open Space Technology and went through three sessions. This went fairly well considering we were only 6 people and all new to this way of working. Some difficulties in coming to a conclusion, but time-boxing still helped to cover the issues.

3. At the end I tried to run a 58 minute agile simulation. I combined XP Game and Scrum Simulation and run a preparation phase with vision creation, then two sprints 10min each and finaly a closure phase. This is OK and could be done again with some slight improvements, but where I made a huge mistake, was that I wanted to wrap up the results from Open Space within simulation. Time pressure from the simulation, new practices coming at fast pace, and meaningfull work at the same time. Not likely.

So my lesson; if you have some very important issue at your hand, do not try to be too clever. Just focus on nailing the one task with the highest priority/value and make sure it gets DONE (aka implemented, tested and documented). If you chose the wrong issue, well buhuu, that's tough.

On the bright side it at least wasn't anything like Dave Nicolette described happening during Jon Kern's presentation. So maybe it was ok from the learning point of view, and at least the journey still continues.

Head up. Reflect. Repeat.

9/16/2006

We Are not Alone

This post by Simon Baker really, really, made my day. It's good to know that the situation I'm currently in is by far not unique.

Can our agility bring about a wider culture change, at least in the program office? Maybe. It depends on the willingness of people to move beyond the comfort zone provided by a command and control environment.

Next week is going to been an interesting one.

9/14/2006

Not So Naive Change Model

Agile methodology is not visible. I do not know what my team is doing. These are complaints often heard from project manager. Ops, I of course mean persons that understand that they are project Managers. Managing is translated into command and control. When saying "not visible" they mean "I can not command", "I can not control", or "I do not understand prototypes, show me paper".

What is described above is the impact of change, and it follows the satir change model. After a smooth start of agile pilot enabling more effective team work, all new kinds of problems start to emerge. Team learns about the actual effort needed in disciplined incremental development versus hacking, but also people who have evaluated their status by how much power they have to command and control (project Managers) may fear loosing their status. All of a sudden product gets developed without screaming, hair pulling and jumping up and down like a freaked out kangaroo. There is no room for the blame game, what is going on here? What is my role in this? A paradigm shift from command and control into trusting and facilitating causes fear among this dying specie of command and control type knowledge-work managers.

One needs to be very carefull not to interpret this new state of chaos as failure in agile intervention. This is excatly what was expected, but fear is a powerfull emotion and when in panic we do irrational things. I on my part fear what happens to a project Manager who in panic starts to act even more irrationaly (compared to my understanding of rational). As we remember from the theory of complex adaptive systems this emerging behavior is of course totally unpredictable...

...fingers crossed everyone, stop-think-act, maybe she gets agile.

9/11/2006

Taming the Big Animal - Agile Intervention in a Large Organization

I made an academic paper about our first larger scale agile experiment available. You can find it via this link (pdf), and it can be found also from the sidebar. Also see the analysis that started this experiment.

Abstract— New Product Development (NPD) today is mainly
managed with plan-driven, relay race type, processes. Today’s
dynamic markets and new technology used in NPD result in a
possibility of benefiting from more adaptive, rugby style,
methods. In the software community methods applying this
approach are commonly called agile methods. In this study I
present experiences from a bottom-up initiative to apply agile
methods for embedded system development in a large
organization using the Stage-Gate® project management
framework. The purpose of the study was to find out whether
agile methods have a chance and how much this type of
organization could benefit from agile methods. Study supported
the earlier research showing that implementing incrementally
some agile practices the project organization was able to improve
the team spirit, motivation level, and additionally to increase
productivity. The affect of agile practices to the Stage-Gate®
framework was minimal. Through wider buy-in and
commitment, the agile development increments could be
synchronized seamlessly to the Stage-Gate® milestones. However
as described earlier in literature, top-down commitment and
changes in organization culture are needed in order to succeed in
process change. The philosophy of agile development is quite
contrary to so called traditional NPD approaches. These changes
in organization culture are also needed in order to fully harness
the power of agile development.

9/09/2006

Can RUP Be Like Switzerland?

At one point debate on agile and more waterfall like sequential process models was claimed to be like religious war. This impression might still be seen in an large organization when agile methods are piloted for the first time. What if the Rational Unified Process (RUP) is the legitimate model for software development in this organization? RUP, being (in my and some others opinion) extremely abstract framework, could easily adapt to pretty much any methodology.

I do not hold a guru status on RUP. I have read the introduction by Kruchten, browsed the net, some papers and that's about it. Yet I propose that RUP could be seen as neutral territory for getting the advocants from both camps to work on common framework in order to let all the flowers bloom.

I know that if I was running a small start-up, and obviously using agile methods full a head, I would not concern my self with RUP because it would not offer me enough. However in an large global organization some level of legitimate system and standardization can be seen necessary, and thus I do not see RUP as bad option. Especially if RUP is already in the house.

RUP has been adopted to agile methods and vice versa starting from the early days, but some major effort has been put to this just lately. Check out:

1. Agile Unified Process (AUP) by Scott Ambler
2. Eclipse Process Framework (EPF) and OpenUP by Eclipse Community

9/02/2006

...About Team Rooms and Pairing

Mishkin Berteig pointed to this web page about setting up a team room. This page pretty much covers everything I have in mind about the subject, especially with the links it has. Pros and cons of the team room are handled. These guys also share my philosophy about forcing these things. If you should force people to do anything, team room and pairing are definately NOT among such things. I believe these issues are automatically brought in when (if) the team jells and learns to work together.

9/01/2006

Our Version of Primetime Emmy Award

It's been awfully quiet around here. It's just because I've been lazy busy.

During the previous Sprint we experimented a practice we called Primetime. Primetime means that immediately after the daily Scrum work was continued in the team room and by pairing for couple of hours. Of course in embedded system development pairing means pair development, not just pair programming.
Yes, yes, we all know that this should be a full day practice. But ... there is lots of other emergent responsibilities, for example maintenance and things like that. At the moment Primetime is the best we can achieve in our environment.

Tom DeMarco highlights the importance of uninterrupted work in his book. The cost of reimmersion time to flow (state of mind when developer "gets her design") is extremely high, and our experiment manifested this.






In our retrospective we easily identified five observations:

  1. People got enthusiast about the design when pairing, and continued way beyond the agreed Primetime
  2. Two people pairing blocks other people from interrupting
  3. Emails, phone calls etc. got postponed
  4. Learning was accelerated because of osmotic communication, and active collaboration
  5. Defects got detected as in review process, thus improving the quality

Within this experiment the team easily achieved Sprint goals, which were set based on earlier velocity. It is too early to make a conclusion, but we decided to keep this practice.